Overview
To support new mechanical and civil engineering programs, UW Tacoma is converting underutilized ground floor space in the GWP-BB-BHS-WCG building complex to laboratory classrooms, a senior design lab and associated support spaces. The project will reduce the footprint of the University Book Store, but it will not otherwise impact retail areas on Pacific Avenue. Construction work is expected to begin in early 2021 and will be complete in time for the 2021-22 academic year.
Design and construction will be led by the University’s project partners, Sellen Construction and McGranahan Architects.
Major Milestones
January 2020
Sellen Construction and McGranahan Architects selected as project deisgn-build team.
January 2021
Project design complete. Building permits submitted.
February 2021
Building permits issued. Commence construction.
August 2021
Construction complete.
September 2021
Project spaces activated for campus use.
Frequently Asked Questions
Construction is scheduled to begin in early 2021.
Project completion is scheduled for September 2021 and spaces will be activated for campus use in October 2021.
The University Book Store anticipates no reduction in service to campus. Textbook sales to a more efficient online format, thereby eliminating the needs for space devoted to textbook storage and display. Other items, such as Husky Gear and school supplies, will still be available for purchase on-site
More Information
For more information on the new engineering labs, contact Shannon Thompson, Project Manager.